Friday, March 10, 2006
The house that Jack supported
So as we enter March, falling slightly behind the original schedule due mainly to the large increase in unanticipated work - replacing unknown rotten wood - the workers (Ray, Dave, Mike) had to borrow Jacks from Justin to temparirly lift the house.
And then replace with new pressure treated.
New Beams!!!